EPA 2022 Construction General Permit (CGP)

For construction sites disturbing 1 acre or more (or part of a larger common plan of development) where EPA is the permitting authority, including New Hampshire, Massachusetts, New Mexico, the District of Columbia, Puerto Rico, Indian country and certain federal facilities.

NOI filing fee
$0 — filed through EPA's NPDES eReporting Tool (NeT)
Wait before digging
14 calendar days after EPA receives a complete NOI
Inspection schedule
Every 7 calendar days, or every 14 days plus within 24 hours of a 0.25-inch storm
Impaired or Tier 2+ waters
Inspections locked to every 7 days plus the 0.25-inch storm trigger (Table 47)
Arid / semi-arid ZIP codes
Seasonally dry period months filled in automatically (Table 32)

The binder follows EPA's own 2022 CGP SWPPP template section for section. Fees and timelines are summarized for planning; confirm current figures with the permitting authority.